Underwater foundations
Contents |
[edit] Introduction
Foundations can often be required for the construction of harbour walls, sea walls, breakwaters, and so on. Underwater foundations, also known as subaqueous foundations, may be used in situations where the use of a cofferdam or caisson is prohibitively expensive or unfeasible.
Typically, dredgers or grabs working from pontoons will excavate the ground and load the spoil into barges. If rock needs to be removed, drill and blast methods can be used, or drilling and cutting by jackhammer. Softer rock formations can be dredged or broken up by air tools and then grabbed. Gravel and sands can be excavated using a suction dredger or ejector tube.
Divers can then place temporary steel formwork, using sandbags to anchor them in place and prevent concrete leakage from under the toe of the form. If the foundation is relatively short and in shallow water, bagged concrete or cement placed in layers may be used as formwork and left in position. Foundations in deeper water may incorporate permanent formwork in the form of precast concrete blocks which are tied in to the foundation.
The concrete mix must have a high degree of workability to maintain a good flow and prevent too much cement being washed out of the mix. This ensures that the leading edge of the concrete is kept moving forward under the pressure of additional material. Extra cement should be added to offset any loss through the water, although too much cement will result in excessive laitance forming on the concrete surface.
[edit] Concrete placing
Concrete is generally placed by one of three methods:
[edit] Placing by tremie
A tremie is a steel tube suspended in the water from a crane. A hopper is fixed to the top end to receive the concrete. The tremie is positioned vertically over the area to be concreted with the lower end resting on the bottom. After the pipe has been filled with concrete it is raised off the bottom to allow it to flow. This should allow the flow to continue to feed the interior of the initial mass.
The flow rate of concrete is controlled by raising and lowering the tremie, but care must be taken not to lift the tremie out of the concrete mass, otherwise the seal will be broken and the concrete will be weakened by water as it rushes out of the pipe. This may result in a damaged surface to the mass of concrete which will need to be removed before work can recommence. One tremie will serve an area of approximately 30 sq. m, and where all the concrete cannot be placed from one position, more than one tremie can be used for simultaneous placing.
For more information, see Tremie.
[edit] Placing by skip
Bottom-opening skips can be used, which are fitted with a top cover held in position by water pressure. The skip is filled with concrete before being gently lowered into the water. On reaching the bottom, the skip is emptied.
If it is lowered too rapidly, the covers may be disturbed and the concrete inside damaged. This is a slower method than a tremie pipe but can be more practical for thin beds, whereas tremies are more appropriate for large pours.
[edit] Pumping
Concrete pumping is a method used when very large concrete pours are required.
Pipe lines typically have a diameter of 110-150 mm and are generally capable of pumping for a distance of 300 m horizontally and 30 m vertically. Pumps may be mounted on a pontoon with an extendable steel boom. The pump works hydraulically with a diesel-driven piston that forces concrete along the pipes.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.